The Whiteman
Village Junction Water Tank is now completed with water finally flowing from the
tank mounted arm from the former "Formby Siding" watering stop on
Wednesday 30th of November - nearly 20 years after the railway acquired it.
In
early 2008 long standing BBR member Ross Parker took on the task
to bring this long term
water tank project to reality. It has has taken a little over three years in the
execution, requiring substantial modifications to the original tank and working
in difficult outdoor conditions. As with all of his projects,
Ross ensured that all aspects of the project were carefully
thought through to enable all the pieces to come together.
With respect to watering steam locomotives, quite early on it had been deemed by
the organisation that procurement of a WAGR water tank from a country town would
not be practical due to sheer size and weight. Likewise a WAGR tank stand was
also in the too hard basket.
Water
Column and Stand at Gnowangerup |
The water column from Gnowangerup was acquired by the
BBR and so on a weekend in May 1992,
a small team of BBR members travelled to
Gnowangerup to dismantle the water column and tank there. The tank was
too badly rusted to save but the rail stand and associated column parts
were dismantled.
This temporary installation was put in
by the WAGR after the line had been closed beyond Gnowangerup in October
1957. Diesels were in use on the line but due to a bumper grain season,
it was deemed necessary to run steam on the line once again and so
watering facilities were required at the end of the line, hence a very
small tank and flimsy looking stand were installed.
|
Gnowangerup
Station from the top of the tank stand at Gnowangerup |
Whilst in the area a short drive was made
out to the former WAGR "Formby Siding" watering stop where there was 2
water tanks remaining insitu. BBR sought permission from the farmer whose
property the siding then resided on, to remove the cast iron arm from the
Eastern Tank at Formby for preservation and use on the BBR .
Formby Siding -
Western tank with somewhat modified arm |
Formby Siding
in August 2003 - thanks to D. Copley for use of this picture. |
Formby Siding -
Eastern Tank with arm recovered for preservation by BBR |
The water
tank which has now been used at Whiteman Village Junction, had been in storage at the Mussel Pool depot for
some time after being sourced from a salvage yard in Hazlemere - thought to have
been used at the Midland Abattoir. It was purchased due it looking not too
dissimilar to a railway style tank, but being not too big to
handle.
For some
years all of these items were stored at the BBR's Mussel Pool depot awaiting the
day they could be restored to be used again for the purpose they were
built.
In early 2008 BBR member Ross Parker agreed to
manage the restoration project.
June 2008 saw the start of some action occurring on the construction of the Tank stand,
with the steel legs intended for use being dug out of the storage compound and
preparation work commencing. The footings for the stand were marked
out and the concrete poured at the location at WVJ station.
Tank stand footings and one of the steel supports
at WVJ |
November
2008 and Greg started beavering away at construction of
the stand and work on the tank itself. The tank was moved
to a location near the workshops for ease of access and the top removed for internal access.. Thanks to PETS for use of their
mobile crane. By December the Tank was ready for sandblasting and primer
By January
2009 most of the column parts had been relocated from the storage
compound, some
repairs were effected to damaged parts and then they were primed and painted. In
December 2009 the Tank was ready and painted - the stand parts were loaded onto
a QBB flat wagon and relocated to WVJ where it was later erected.The Tank also
was transported by rail to the WVJ site.
After some
delays with construction of a new roof, it was during August/September of 2011
that the new tank roof was fitted and then placement of the Water tank on its stand at
Whiteman Village Junction took place, enabling the erection of the associated tank mounted and free
standing water columns to commence.
After several months of installation work of
the tank mounted column, plumbing and fittings, on Wednesday 30th of November
2011 water flowed from the tank mounted column once again. It is hoped to soon
be able to install the free standing column from Gnowangerup, for use on 1 road
across the tracks.
New tank in location at
WVJ station |
Tank Mounted Column in
place on the tank |
Water flows for the
first time |
The water tank will be a great asset to the
railway in future steam seasons, as it will enable our steam locomotives to be
filled with rain water (rather than bore water). It has a back up storage
and pumping system in place to keep the tank supplied with water harvested from
the Revolutions Museum roofing. The use of rain water should require less
chemical additive to the water with financial & environmental
benefits. Apart from a slight leak at the outlet (which will be fixed) for
the future 1 road water column, everything works well. A "shroud" or
metal cover for the chain wheel is yet to be fabricated - this will prevent the
chain from coming off the wheel, which if it should occur when the valve is
open, could pose quite a damp problem. A separate chain has been provided for
swinging the crane arm in and out.
This
structure adds another interesting heritage aspect to the already impressive
rail precinct at Whiteman Village Junction. Ross related "When I
tested this with the Perry (Betty Thompson), it filled the Right Hand Side tank
to overflowing in 43 seconds! The transfer pipe (between the 2 tanks) just
isn't big enough to transfer the water to the offside tank quickly enough! This
will of course also provide another interesting operational aspect for members
and visitors to the railway
Ross would
like to thank Greg Harris, who put in many hours of laser cutting and welding in
trying conditions. Thanks also go to Brian Rourke, Kim Parker, Tony Gauci,
Richard and Ken Cheeseman, John Johnstone and Simon Mead for their assistance. A
special thanks goes to Bob Davies and his company BG&E as the structural
engineer for his guidance and oversight on the modifications and erection.